Pearson Rd, Yatala

Project Details

  • Date: 01.02.2016
  • Location: Pearson Rd, Yatala
  • Value: $1,580,000
  • Category: Porphyry

Pearson Rd, Yatala

 

At the beginning of October, Boulder Walls commenced construction of 5,000m2 of rock wall for BMD at the Pearson Rd, Yatala site.

As part of the Yatala Central development, the wall was constructed using our porphyry bush rock and ranges in height up to 6 metres. 80% of the wall has been built with a 20kPa loading to allow for the site’s future industrial use.

The project was completed in January 2016 with further construction to commence throughout the year.

Pearson Rd, Yatala

Michael Shield

Construction Manager